Building Scaffolding in the Tidal Waters of Loch Linnhe
M8 Scaffolding was appointed by Charles Brand, a Northern Ireland-based construction company, to provide scaffolding for stone cladding works at Corran Ferry’s Nether Lochaber terminal, near Fort William.
The work involved providing access for stonemasons installing stonework along the newly constructed harbour frontage on Loch Linnhe.
On paper, a relatively straightforward scaffolding job.
There was just one complication. We had to build it in the loch.
Building Scaffolding in the Tidal Waters of Loch Linnhe
Corran Ferry sits at the Corran Narrows, where the ferry crosses Loch Linnhe between Nether Lochaber and Ardgour. Working at the water’s edge presented some unusual challenges, particularly as the scaffold had to be erected within an area affected by the changing tides.
Our team had to plan the installation around low tide, making the most of the limited working time before the water returned.
The location also called for a specially designed scaffold. With no conventional solid foundation available, a timber base was constructed to support the installation. Concrete blocks were then used as ballast to help keep the structure in position and prevent movement as the water level changed.
The last thing anyone wanted was to see the scaffolding heading off down Loch Linnhe.
It was an unusual arrangement, but one that had to be properly considered from the outset. The scaffold needed to provide a suitable working platform for the stonemasons while remaining stable in conditions very different from those encountered on a typical construction site.
Specialist Scaffolding for Challenging Locations
Projects like Corran Ferry demonstrate why scaffolding isn’t always as straightforward as it might appear.
The basic requirement was familiar enough: provide access so that another trade could carry out its work. But the location changed how we approached the installation, from the initial scaffold design through to the timing of the work and the measures needed to secure the structure.
For M8 Scaffolding, the important part was understanding those challenges before arriving on site.
With our Fort William depot supporting projects throughout Lochaber and the Western Highlands, we’re accustomed to working in locations where access and ground conditions aren’t always ideal.
Sometimes that means adapting a scaffold to suit a difficult building. On this occasion, it meant working around the tide and making sure the installation stayed firmly in place.
Not quite your everyday scaffolding job.