Scaffold for Toilet Block build in Fort William

We had been approached by a Commercial Contractor to support with the build of a new toilet block structure at Bunree Caravan and Motorhome Campsite in Onich, Fort William.

The concrete structure had been built, and we had 2 days to erect the scaffold to allow the pre-fabricated timber kit to be brought in. Working with the joiners and site manager, we adjusted the build to allow an opening to bring the kit in. We will return in ten days to finish the small section and install edge protection to allow safe access to the new roof.

A wonderful place to work, but as is the nature of an open area overlooking Loch Linne, the weather was as wet as we have ever worked in…

 

 

Share the Post:

Related Posts

A scaffolding service that reaches new heights in service and value

Get in touch and find out how M8 Scaffolding can meet your scaffolding requirements in Glasgow, central Scotland and Fort William and the surrounding areas.